From the calculation (offer) it is possible to create contracts:
By gradually toggling the detailed state:
The procedure is not recommended. If the Status field is set for contract number assignment on the financing model, the contract is renumbered if the user sets this detailed status on the model.
Use the function (button) Create contract from calculation (is visible only for detailed contract statuses with Calculation=A, otherwise not)
Recommended actions
A new entity is created by copying, whereby:
It will have a number according to the Contract Numbering settings on the Financing Model
It will have a detailed status according to the Initial Detailed Contract Status setting in OneCore Settings
The original offer is preserved, it is possible to create any number of contracts from it
The contract creation date is automatically filled in as the workdate
Click on Create Contract from Calculation
After confirmation, the system performs a flag check Mandatory Quote Approval in Settings OneCore. If the value will be:
Yes:
Checks to see if the History connivance There is a record for the offer:
Financing Contract No. = same as the quote number from which the process is started
Approval Status = Approved
Active = Yes
If:
There is no (i.e. the offer does not have a valid approval)
Displays the message "The offer does not have a valid approval. (Offer No. .. Contract No.... doesn't have valid approval.)". After confirmation, it closes the message and does not continue the process
Exists
Checks already created contracts from the menu:
Filters contracts to Source Calculation No., for which:
Change Copy = No
Calculation Variant = No
Calculation on Detailed contract status = No
and find out their number
This number should be < than Number of Contracts z Approval History
If:
Pays
Moving on to the next step
Does not apply
Displays the message "The number of contracts has been exhausted. (The number of contracts has been drawn.)". It does not continue after the message is closed
Well
Proceeds to the next check.
Approval of the offer is described in a special chapter Schválení nabídky
It proceeds to check if there is an allowed transition from the detailed calculation status to the initial detailed contract status (inic.det.contract status is set in OneCore Setup):
If it doesn't exist, it displays the message:
If it exists, it creates a contract and asks if we want to open it:
Once confirmed, the new contract card will open.
The contract was created by copying the offer (including all related entities). The created contract will have the following differences from the offer:
the contract number from the contract number series according to the settings in the Financing Model, the Contract Nos field. At the same time, the subject is renumbered, or the contract number is added to all related entities.
detailed status according to the settings in OneCore Setup, field Initiale Detailed Contract Status
Completed Contract Creation Date = Workdate of the system
filled in Source Calculation No.=number of the calculation from which the contract was created
filled in Date Created (Others tab) = sysdate
Copies records (the documents themselves will not be copied) Attachments belonging to the offer to the contract (so that they are available with the contract):
ID (48) - gets a new one
Table ID (2) - keep original
No. (3):
for Table ID (2)=4026397 - add new contract number
for Table ID (2)=4026560 - add the object number of the new contract
Copies the values of all other fields in the table, but does not change them
Course attachments are copied in a similar way