There are two ways to interrupt accounting depreciation:
User
Batch Job for Asset Cards for to Financing Contracts/Financed Object Contracts.
In order to be able to set the period of interruption of accounting depreciation from a specific date, a new field "Depreciation Interrupt from" has been added to the depreciation book.
The standard field "Depreciations Interrupted up to" is used to terminate the suspension of depreciation interruption.
To calculate the interruption of accounting depreciation "from" date, the "Calculate Depreciation" task has been modified. A detailed description of the principle of adjustment is described in the chapter Výpočet odpisů
On Tax depreciation is not affected by Depreciation does not have any impact on the new field for interrupting depreciation from or by , nor does modifying the Calculate Depreciation task have any impact.
User Interruption of Accounting Depreciation
User entry of the date for the interruption of accounting depreciation "from" should be used only for asset cards that are not related to financing contracts/financed objects. That is, for other asset cards Other Asset Cards.
In the Account Depreciation Book, in the "Depreciation Interrupt from" field, you can enter the date from which accounting depreciation should be interrupted for the asset card.
...
Above the field, there is an additional check to see if make sure that the entered date does not fall within a period for which accounting depreciation has already been posted. If the date is entered by the user and the check finds that the entered date falls within the period for which depreciation is already posted, an information window is displayed asking whether the already posted depreciation should be deposted:
If the option is confirmed, lines the rows with the amount of posted depreciation for the period will be suggested to the Fixed Asset G/L Journals and the entered date will be entered in the "Depreciation Interrupt from" field
If No is selected, "only" the entered date is entered in the "Depreciation Interrupt from" field.
Suggested lines in the Fixed Asset G/L Journals must then be posted to the user.
...
Interrupt Accounting Depreciation Batch Job
This batch job resolves the interruption of accounting depreciation on the asset card of the financing contract Asset Card for Financing Contract / financed object.
Reasons for discontinuing to interrupt accounting depreciation:
Contract Termination
theft
Total damage, total economic damage.
For the Interruption of Accounting Depreciations batch job, a Batch Job Card must be created with Batch Job Type = FA – Interrupt to set up filters for detailed contract statuses, financing product types, and depreciation book code. A detailed description of the card settings is described in the chapter Nastavení Finance .
According to the set filters in the batch job, the number of the Fixed Asset Card No. from the Financed Object field is searched for from the Fixed Asset Card No. field.
First, the The task first checks whether the conditions for interruption suspension of depreciation in the accounting book of depreciation are already entered in the found asset card, i.e. in the "Depreciation Interrupt from" field, a date equal to the Termination Date from the currently related contract is entered. It also checks whether a date is entered in the "Depreciations Interrupted up to" field and that the date is less than the Termination Date of the currently related contract. This will show find out that the previous conditions for suspension of depreciation interruption have already expired and delete deletes both dates in order to set up new conditions for suspension of depreciation interruption, i.e. enter in the field "Depreciation Interrupt from" enters the Terminated Date from the currently related contract in the "Depreciation Interrupt from" field.
A detailed description of the process of processing the task is described in in chapter https://iao.atlassian.net/wiki/spaces/OCDOC/pages/edit-v2/32440556#Proces-zpracov%C3%A1n%C3%AD-%C3%BAlohy
The new field "Depreciation Interrupt from" affects the correct calculation of accounting depreciation, also with regard to the possible start of depreciation interruption retrospectively, i.e. in the period for which accounting depreciation has already been posted. Therefore, it was necessary to modify the Calculate Depreciation task had to be modified. Modifying . Modification of this task is described in chapter https://iao.atlassian.net/wiki/spaces/OCDOC/pages/32604443/V+po+et+odpis#%C3%9A%C4%8Detn%C3%AD-odpisy
...
by transferring to a new contract. This case is solved by a new task on the subject item card "Asset Card Transfer" described in chapterÚloha Převod karty majetku
Successful resolution of theft resolution – due to the rare occurrence of this situation, the system does not handle automatic processing. Manual processing is required. The Depreciation Interrupt from field is editable.
...
in the Fixed Asset overview , it is located in the Process -> Interruption of Accounting Depreciations menu or in the Actions menu, where the tasks can be rearranged by the user using the Personalize function
Search using the system magnifierSystem Magnifier.
Dependencies and assumptions
The dependency is on the batch job setup for interrupting accounting depreciation, i.e. with Batch Job Type = FA – Interrupt.
Another important dependence dependency is that in the event of theft or total/economic damage, the detailed status of the contract changes. Correct processing of the task depends on the settings of specific detailed contract statuses.
...
When the Interruption of Accounting Depreciations task is invoked, a dialog box is displayed in which where you can set:
Post, by switching to Yes, the proposed lines will be posted according to the job process
Filters on fields from the contract header.
After starting running the job with by clicking the OK button, the job looks into the Batch Jobs Setup List (API Batch Jobs Setup List 404786 ) table and looks for the job card with Batch Job Type = Dm – Interrupt (FA). If it does not find it, it terminates processing and an error message. If it finds it, it continues processing as follows:
Applies filters to Financing Product Type Filter, Contract Status Filter, and Detail Contract Status Filter according to the settings in the batch job
If a filter on the for Contract No. (No.) or another filter on for a field from the contract header is specified in the task dialog, the filter is applied according to the specified
Checks the Calculation field in the Detailed Contract Status. If Yes, it stops processing the contract and moves on to processing the next contract. If it is No, it continues to process the next steps of the process
Checks the contract for the existence of a date in the Termination Date field. If a date exists, the task continues to be processed. In the absence of a date, the processing of the contract is will be terminated and the processing of the next contract continueswill continue
He looks at the Contract Object Item Card and looks up finds the Fixed Asset Number. If there is a blank value in the Fixed asset number field, writes to the Fixed Assets Log (4047588) notification "Fixed Asset No. must have a value in Financed Object: No.=xxxxxx. It cannot be zero or empty"
If there is a field Blocked = Yes field in the header of the found FA card, it will terminate the processing of the contract and continue processing the next contract
On the asset card, checks check to see if the Depreciation Ledger is in the there is a Disposed Of = No field in the Depreciation Book Ledger. In the event of a match, processing continues according to the next steps of the job. In the event case of a disagreement, it terminates the process and proceeds with the processing of another continues to process the next contract
On the asset card, he checks whether the conditions for suspension of depreciation in the depreciation accounting book are not entered in the found asset card, i.e. in the "Depreciation Interrupt from" field, a date equal to the Early Termination Date from the contract is entered. In the event that:
If the value of the (date) field is empty, enters writes the Termination Date from the contract into the field
The value of the (date) field is not equal, so it checks to see if the a date is entered in the "Depreciations Interrupted up to" field. If the result of the check is:
the entered date entered is less than the Termination Date of from the contract. This will show determine that the previous conditions for suspension of suspending depreciation have already expired and deletes both dates. In the "Depreciation Interrupt from" field, enter the Termination Date found from the contract
the specified entered a date higher than the Termination Date from the contract. Writes to Fixed Assets Log Error message with the text "Depreciation Book 1 - ACCOUNTING for Fixed Asset No. xxxxxx - Depreciation Interrupted Until interrupted until is higher than the Termination Date on the financing contract." (Depreciation Book 1-ÚČETNÍ for FA No. xxxxxx - Depreciations Interrupted up to is higher than Termination Date on Financing Contract.)
The value of the (date) field is equal, so it ends the processing process and continues processing the next contract
If the Post boolean is in the Jobs dialog box:
= Yes, so it does:
In the Default (Accounting) Depreciation Book, checks if the Use Same FA+G/L Posting Dates field = Yes. If the condition is met, it switches to No and continues processing to process the next steps. At the end of contract processing, it reverts to the original settings. If the condition is not met, it continues to process the next steps
Reverse depreciation if the interruption date falls within the period with posted depreciation and the Termination Date is different from the Last Depreciation Date in the depreciation bookDepreciation Book of Accounts. That is, it suggests lines rows with the amount of posted depreciation for the period to the Fixed Asset G/L Journals (G/L JournalsFA) and posts the proposed lines. Entering Enters the 1st open posting period as the Posting Date if the original period is closed, otherwise it will use uses the same date as the canceled item. FA Posting Date enters the 1st open asset period if the original period is closed, otherwise it uses the same date as the canceled entryitem. Uses the Document No. from the journal batch setup for accounting depreciation
If the Termination Date is different from the Last Depreciation Date in the Depreciation Book of Accounts, it suggests lines rows in the Fixed Asset G/L Journal (FA) Journals for depreciation on the specified date "Suspension of depreciation from" and posts the proposed lines. Enters the 1st open accounting period as the Posting Date if the original period is closed, otherwise it will use uses the same date as the Termination Date on the contract. In the description, he enters enter "Depreciation according to data revision". Enters Document No. enters the same as for the depreciation reversal lines
= No, so:
If there is no interruption of it is not a case of suspending depreciation to the past, it performs the same actions as for "Yes", but does not post the proposed lines in the Fixed Asset G/L Journals. Suggested journal lines must be posted by the user
If the depreciation interruption is concernedinterrupted to the past, the user must turn off the Check check on the Default (Accounting) Depreciation Book Use Same FA+G/L Posting Dates before running the task and turn the check back on after all entries have been posted. Subsequently, run the task. The task suggests reversing depreciation according to the same principle that is described in the paragraph for direct posting paragraph. Suggested reverse depreciation reversal lines must be posted on a user basis. Subsequently, the task to generate depreciation must be run. In the dialog window, the FA Posting Date is entered in the last previous month and the Posting Date is entered in the first current month. The proposed depreciation lines must then again be posted again by to the user
They end the process and proceed to process the next contract.
After the job task ends, it is recommended to always check the Fixed Asset Error Log (FA) to see if any contract processing has been terminated due to an error found. After resolving/deleting the written error report is resolved/deleted, the task can be run repeatedly.
To run a task in
...
Task Scheduler
Task Problem No. 4047510 It is possible to run it within the task scheduler Task Scheduler by displaying the Send to scheduler Scheduler option after the task starts, then opening a dialog box with scheduler settings options.
...
Job Queue Entries to determine whether the job was terminated by an error message. After solving/removing the written error, the task can be started again using the Restart button